Target Construction Schedule

Work Area Description Duration Start Time
Closure of Runway 16L 77 days January 2019
1 Taxiway B from Taxiway C to Taxiway D 42 days January 2019
2 Taxiway B from Taxilane B1 to Taxiway E 35 days February 2019
2A Shortening of Runway 16R 5 days March 2019
3 Taxiway B south of second Signature East entrance 35 days March 2019
4 Taxiway B from Taxiway Q to second Signature East Entrance 28 days May 2019
4A Re-lengthening of Runway 16R 5 days June 2019
Closure of Runway 16L 166 days June 2019
5 and 5A Marking of temporary Taxiway T 5 days June 2019
6 Taxiway B from Taxiway E to Taxilane B2 70 days June 2019
7 Taxiway B from Taxiway G to Taxiway J 35 days August 2019
8A Taxiway B from Taxiway J to Taxiway N 5 days September 2019
8B Remarking of Runway 16L 5 days October 2019
9 Taxiway B from Clay Lacy entrance to Taxiway Q 70 days November 2019
10 Taxiway B final marking 21 days February 2020
Project completion End of March 2020

Operational Impacts
The target construction schedule includes a 77-day closure of the 4,000-foot Runway 16L, used mainly by piston aircraft, beginning in early January 2019. A second, 166-day closure of Runway 16L is scheduled to commence in early June 2019 when it will be utilized as a temporary taxiway. During these times, operations will be directed to the 8,000-foot Runway 16R.

In addition, a 73-day shortening of Runway 16R is slated to commence in late March 2019. During this time, there will be a minimum of 5,000 feet available for aircraft arrivals and 5,209 feet available for aircraft departures.