TAXIWAYS RECONSTRUCTION PROJECT, Year 1 – Taxiways D, E, F, Q

PROJECT OVERVIEW

Description

In February 2025, work will commence on a $15.4 million, 6-month project to reconstruct segments of Taxiways D, E, F, and Q. This project will deliver important upgrades and extended lifespan to the airfield facilities that contribute to VNY’s world-class status. Improvements will be phased to maximize federal grant reimbursements and minimize operational impacts during construction.

Runway / Taxiway Closure Map and Height Restrictions
Information
Photo Gallery

 

 

TAXIWAYS RECONSTRUCTION PROJECT, Year 2 – Taxiways C, H, M, N, P

PROJECT OVERVIEW

Description

In early October 2025, work will commence on a $18.8 million, 5-month project to reconstruct segments of Taxiways C, H, M, N, and P. This project will deliver important upgrades and extended lifespan to the airfield facilities that contribute to VNY’s world-class status. Improvements will be phased to maximize federal grant reimbursements and minimize operational impacts during construction.

Work will include reconstruction of:

  • Taxiway C from Runway 16R-34L to 16L-34R
  • Taxiways H, M, and N
  • Taxiway P between Taxiway B and Runway 16R-34L
Runway / Taxiway Closure Map and Height Restrictions
  • Phase 1 (10/ 9/2025 to 11/6/2025)
  • Phase 1B (11/2/2025 to 11/6/2025)
  • Phase 2 (11/9/2025 to 12/3/2025) No closures or work will occur during the Thanksgiving holiday period (November 11–30)
  • Phase 2B (12/ 7/2025 to 12/17/2025) No closures or work will occur over the Christmas and New Year holidays (December 18 – January 4)
  • Phase 3 (01/04/2026 to 01/25/2026)
  • Phase 3B (01/25/2026 to 02/04/2026)